RECTIFICATION WORKS

Ripa Concrete Cutting was called in by Shape Australia when a reaction wall inside a testing facility within UTS failed under pour causing the finish to be unviable.

A methodology was put in place for the corrections which entailed Ripa Concrete Cutting using their Track Mounted Wall Saw to saw cut every 10mm at a tolerance of 1mm. In order for this to be done, Ripa Concrete Cutting had to make custom structural steel jigs on a roller system to mount the Wall Saw too in order to achieve the desired tolerance.

This equated to over 2.4km of saw cutting.

We also designed and installed a plastic bubble prior to commencement of works which assisted with slurry and dust control. The works took 2 weeks to complete and is now able to be used as intended.

Want to Know More?

Find out more about the services we provided Shape Australia by clicking on the links below.

Wall Sawing

UTS-Suspension-Lab-1 (1).jpg

Our staff are here to help.

Request A Free Quote Today

  • Facebook
  • LinkedIn
  • YouTube
  • Instagram

©Copyright 2020 - Ripa Concrete Cutting Pty Ltd

ABN: 79 110 352 862

Ripa Concrete Cutting Logo.png