University of Technology (UTS) Tech Lab

Project Commence Date: October 2020

Project Completion Date: October 2020

RECTIFICATION WORKS

Ripa Concrete Cutting was called in by Shape Australia when a reaction wall inside a testing facility within UTS failed under pour causing the finish to be unviable.

A methodology was put in place for the corrections which entailed Ripa Concrete Cutting using their Track Mounted Wall Saw to saw cut every 10mm at a tolerance of 1mm. In order for this to be done, Ripa Concrete Cutting had to make custom structural steel jigs on a roller system to mount the Wall Saw too in order to achieve the desired tolerance.

This equated to over 2.4km of saw cutting.

We also designed and installed a plastic bubble prior to commencement of works which assisted with slurry and dust control. The works took 2 weeks to complete and is now able to be used as intended.

IMG_0266
IMG_0266

press to zoom
IMG_0274
IMG_0274

press to zoom
IMG_5052_copy
IMG_5052_copy

press to zoom
IMG_0266
IMG_0266

press to zoom
1/8

Want to Know More?

Find out more about the services we provided Shape Australia by clicking on the links below.

Wall Sawing

IMG_0292.JPEG
UTS-Suspension-Lab-1 (1).jpg

Our staff are here to help.

Request A Free Quote Today